Clearing 5 Acres in Union Grove

We estimated this particular land clearing project would take around three days, and that’s exactly where we ended up. However, it came pretty close to turning into a four-day job.
One of the biggest factors was the amount of hardwood mixed throughout the property. Hardwoods can take considerably more time to mulch than lighter brush, undergrowth, and smaller vegetation.
That’s also one of the challenges that comes with quoting larger forestry mulching projects. You can walk a property, look at the density, evaluate the size of the trees and brush, and make a solid estimate—but sometimes you don’t know exactly what you’re dealing with until the machine gets into it.
We always try to give our customers the most accurate estimate possible based on what we can see during the initial property visit. We quoted this project for three days, and we’re proud that we were able to get all five acres completed within that timeframe.